ECONOMIC-GREEN: FASTFOOT® - the NUMBERS say it all

Green doesn't have to be expensive. Fastfoot® leads to dramatic savings as proven by the Flowers Group in the Cayman Islands. See the spreadsheet below for details.

And Fastfoot® prevents moisture migration through the footing into the building interior. Click here for details.

FASTFOOT® LUMBER
$1.34 per running foot $4.67 per running foot
Fastfoot on Cayman Islands Lumber formed footigns

The Williams Construction Crew, builders in the Grand Cayman Island experienced three-fold savings with Fastfoot®. In addition, the fabric prevented contamination of the concrete with muddy water, leading to a much stronger concrete.

Flowers GroupFastfoot® was supplied by the Flowers Group. Stu Oates, technical representative, is excited to introduce fabric forming to the islands, "All our lumber has to be imported, so any product that reduces the amount of lumber is a huge cost saver and a solid green winner!"

The Flowers Group has been hosting the Flowers Sea Swim for 17 years, which this year had a record 768 swimmers, 5 Olympians, and 13 countries represented. For a fascinating history of the Flowers Group and the initiatives of Clarence Flowers, please click here.

Footing height (in) 16
Footing width (in) 24
Footing length (ft)  356
Labor cost per hour (Cayman$)  $ 24

  FASTFOOT® LUMBER
Material costs Unit Cost Qty Reuse  $  Qty Reuse  $ 
Lumber cost (2x12 + 2x4) ft  $     2.03 0 1  $      -   712 2  $      724
Form stakes (5/8" rebar) each  $     1.17 119 20  $        7 119 1  $      139
Fastfoot® ft²  $     0.07 1,839 1  $    127 0 -  $        -  
Fastfoot® screed board ft  $     0.42 712 10  $      30 0 -  $        -  
Disposal of lumber ft³  $     1.50 3 1  $        5 61 1  $        91
Material subtotal    $   168  $     954
       
Labor  Cost/hr  Hours  $  Hours  $ 
Level excavation hour  $   24.00 0  $      -   6  $      144
Drive stakes hour  $   24.00 4  $      95 4  $        95
Set up lumber or screeds hour  $   24.00 6  $    132 11  $      264
Install fabric hour  $   24.00 2  $      57 0  $        -  
Strip forms hour  $   24.00 1  $      24 4  $        96
Clean forms hour  $   24.00 0  $      -   2  $        48
Remove, store forms hour  $   24.00 0    $      -   3    $        62
Labor subtotal   13  $   308 24  $     709
       
TOTAL - Cayman $          $   477      $  1,664
TOTAL - Cayman $/lin ft          $  1.34      $    4.67

Note: the Cayman $ equals approximately $1.20 US.